PROBLEM
.......Industrial Contract requiring Heat Resistant Resin
SOLUTION Most chemical resistant resins do not lend themselves to factory wet out as they tend to cure rapidly in mass. Why don't you rent the Impregnation trailer, wet out on site, typically 400ft of 8" x 6mm in 1 hr !....Shoot the liner in place within a couple of minutes and then cure.......>>>Click on Video to Watch !!!
PROBLEM
....Cured in Place Lining down a Steep Slope ???
SOLUTION Lining down steep slopes can present two problems. Usually this could mean a very elaborate scaffold structure is required for stability purposes. The second problem is the head pressure of water at the downstream end is likely to burst the bag. Rent an Air inverter in and blow the problems away!!! .......>>>Click on Video to Watch !!!
CALL NOW FOR GLOBAL & NATIONWIDE SALES & RENTAL SERVICE 888 639 7717
The Specialty Rental Shop for CIPP Contractors
MORE EXAMPLES ???
SCROLL DOWN
SOLUTION An authoritative figure in the Trenchless Relining world once said any CIPP shot under 750 feet is a loss leader. At today's current prices he is possibly right...Water inversion takes typically 2 -6 hours to set up...Air Inversion takes 5min !!!!.......>>>Click on Video to Watch !!!
MORE EXAMPLES ???
SCROLL DOWN
PROBLEM
Short Lining Shots..."Here There and Everywhere"
PROBLEM
.......Sewer Renovation in Easements.....
SOLUTION Park the inverter at the closest point and shoot the "dry end" above ground, trunk it till the manhole, then insert wet end into pipe run...Cheaper than removing a garage !!! .......>>>Click on Video to Watch !!!